PROJECT
Role:
Lead UX Designer (with one associate)
Deliverables: Hi-Fi Mockups, Prototype
Design System: Existing
Device: Desktop Web Only

CHALLENGE
We needed an application to orchestrate and facilitate the production of rich content by an army of professionals for over 300,000 neighborhoods, parks, and, schools across America.

We were handed 3 sprints and a business flow diagram by the CIO. We were to stand up an application that would enable more than 2,000 contractors to generate images, descriptions, scripts, voice-overs, and videos.

Development was given 2 of the 3 sprints, and every developer on our floor was pulled from their projects (~50 devs). Design was given one sprint and I received an associate designer to help.

Ok, go.

ACTION
This was a high speed project. Nailing down business requirements for something that had no existing users and no one had done before, proved to be mostly a shot in the dark. We had virtually nothing to go off of and even less time, so we made our best guesses with what we had. Design time bled into development time, so developers were working from shifting designs. It was an intense experience for everyone involved.

Using contractors to accomplish this massive undertaking added an exponential level of complexity to the application, both on the tech side and the experience side, as contractors, for legal reasons, weren’t allowed to access our systems. That meant no email, no phone, no messaging and a completely separate log-in portal that would be (basically) iFramed in to our existing application for employees.

It also meant that everything a contractor made or touched had to be checked and re-checked. It meant they had to be constantly managed, because they could work when they wanted, and they had no permissions or authority.

User roles to account for:

1) Content Manager (employees)

2) Content Writer (contractors)

3) Copy Editor (contractors)

4) Photographer (employees and contractors)

5) Photography Manager (employees)

6) Voice-Over Artist (contractors)

7) Video Editor (employees and contractors)

8) Quality Assurance (employees)

The application would operate as a place to house the content and facilitate workflow, allowing roles to hand off to one another.

We gave users a dashboard of assignments and, based on existing design standards, we came up with a relatively simple interface for inputting content into the assignments (shown). Admittedly, the interface is a little dry and text heavy, as we would not have any photos at the beginning. Working out what images to show as thumbnails was a feature we had planned to come back to. I knew differentiation would be a problem, so the best we could do was use icons to differentiate the assignment types. I wanted to bring the map up in the hierarchy to provide more context, but I was vetoed on that issue. The users have sticky jump-links in the top menu.  

The permissions and business logic behind each button, each role, and behind each handoff, however, became a huge challenge both for our team and the users. Advocating for simplifying this overly complicated system of hand-offs and permissions became a main objective of mine throughout this project.

We only had a small group of newly promoted content managers to work with, and they had no idea what to expect with their new jobs. I showed designs to them before sending to development and they seemed to understand the basic interface. However, without having started their brand new job and not knowing much about it, feedback was limited.

RESULT
Miraculously the product was delivered on time and (mostly) according to spec; an amazing feat in itself, given the level of complexity and the incredibly short timeline. In beta testing with the content managers, we assigned each of them a role (photographer, voice over artist, etc) and had them sit in a room and pass assignments around. It was a little confusing for them at first, but they got the hang of it. One thing was becoming clear though: with so much volume, we were going to need to provide a more transparent overview into the status of any given assignment.

That said, the MVP did what it was intended to do: it enabled the employees and contractors we had already hired to get started on the massive task ahead.

Because we built custom software to support completely untested business processes, the project struggled as hard realities surfaced and created tectonic shifts in the business requirements.

The product manager and I continued to support the product, keeping close contact with users, plugging holes, and fixing the experience as things changed.

As this went on, however, the application began to look like Franken-ware, with vestigial features, unexpected orifices, and less-than-ideal work-arounds; very difficult for any UX designer to watch – like watching your baby slow-fall down the stairs.

We listened to our users’ challenges carefully, and proposed thoughtful solutions, but after the initial push, the maintenance team for this project was small and there were often too many competing priorities to actually be able to deliver on the pain points we were hearing from our users. 

Eventually, this reached a breaking point, and contractors were let go, which was unfortunate, but simplified things immensely. Roles were redefined, workflow was simplified, and hierarchy flattened. We could eliminate several features rendered useless, and add a few more helpful ones. I had been advocating to start over for approximately two months before we were finally given the go-ahead. Time to burn it down and redesign. What a relief.

As of this writing, much of the neighborhood content has been released to the homes.com consumer facing site. Looking at the page, it’s easy to take for granted the sheer number of people, specializations, effort, and technology that go into bringing this sort of rich media and content to life behind the scenes.

Bellevue neighborhood from homes.come:  Bellevue

CONTENT DEVELOPMENT PROJECT

CoStar acquired Homes.com, and in early 2022 started renovating the small residential application to compete with Zillow, Redfin, and Realtor.com.

One of the many differentiating features for Homes will be rich content, including descriptions, images, and professional videos for every park, school, and neighborhood across the U.S.

Orchestrating the development of this much content on such an aggressive timeline, was a MASSIVE undertaking with precious few product resources. For the most part, I was the sole designer on this project, which would consume the second half of my two-year tenure at CoStar.